Chapter 6 — Piezometers and Pore-Pressure Monitoring

6.1 Why pore pressure is central

Pore pressure — the pressure of water within soil, rock, or concrete — drives seepage, slope stability, and uplift. It is among the most important quantities monitored on dams. A rise in pore pressure can precede both internal erosion and slope failure.

6.2 Types of piezometers

Type Principle Best for
Vibrating-wire (VW) Frequency change of a tensioned wire Long-term automated monitoring; robust
Pneumatic Gas pressure balances water pressure Remote/ungaged locations, no power
Standpipe (open) Water level in a pipe Simple, direct, but slow to equalize
Hydraulic (twin-tube) Liquid-column balance Multiple points, established method

Saturation is everything

An unsaturated VW piezometer reads nonsense. The saturation procedure — removing air from the porous tip and connecting tube — must be done carefully at installation. A piezometer that was never properly saturated is a silent gap in the program. (See Dunnicliff Ch. 9.)

6.3 Where to place them

Piezometer location follows the failure modes:

  • Downstream of cores and cutoffs to detect seepage buildup.
  • In the foundation beneath and downstream of the dam.
  • At the phreatic surface to track the seepage line through the embankment.
  • At the base of concrete dams to monitor uplift.

Multiple depths at a single borehole (multi-level or MPBX-style) reveal the vertical pore-pressure profile.

6.4 Installation essentials

  • Drill and case the borehole; avoid smearing the surrounding soil.
  • Place the tip in the stratum of interest with proper filter packs.
  • Backfill and seal to prevent short-circuiting of water along the borehole.
  • Saturate VW and pneumatic tips fully.
  • Record installation details — depth, stratum, orientation, date — in the permanent file.

6.5 Reading and interpreting

Readings are typically converted to piezometric head (elevation of the equivalent water surface). Key interpretations:

  • Steady rise without a reservoir rise → possible blockage, seepage increase, or sensor fault.
  • Pore pressure lag relative to reservoir → indicates drainage path and permeability.
  • Exceedance of the phreatic line used in design → stability concern.

6.6 Common problems

  • Air entry / desaturation → drifting or unresponsive readings.
  • Borehole short-circuit → reads the wrong zone.
  • Freeze damage → lost winter data in cold climates.
  • Electrical/cable failure → most common automated-instrument failure.

6.7 Key takeaways

  • Pore pressure drives seepage, slope stability, and uplift — monitor it carefully.
  • Saturate VW and pneumatic tips properly; an unsaturated piezometer is useless.
  • Place instruments where failure modes manifest; use multi-level installations.
  • Interpret as piezometric head and compare against the design phreatic surface.